1. Planned % Complete Values as at a particular date
Then add some Forecasting calculations for Estimate at Completion, Estimate to Complete, Variance at Completion and To-Complete Performance Index.
Key EVM Concepts:
- Planned Value (PV) / Budgeted Cost of Work Scheduled (BCWS)
- The estimated value of work planned to be completed by a specific date.
- Formula: PV=Budget at Completion (BAC)×Planned % CompletePV=Budget at Completion (BAC)×Planned % Complete
- Earned Value (EV) / Budgeted Cost of Work Performed (BCWP)
- The value of work actually completed at a given point in time.
- Formula: EV=BAC×Actual % CompleteEV=BAC×Actual % Complete
- Actual Cost (AC) / Actual Cost of Work Performed (ACWP)
- The actual cost incurred for the work completed.
Key Performance Metrics:
- Cost Variance (CV)
- Measures cost performance.
- Formula: CV=EV−ACCV=EV−AC
- Interpretation:
- CV > 0 (Positive): Under budget
- CV < 0 (Negative): Over budget
- Schedule Variance (SV)
- Measures schedule performance.
- Formula: SV=EV−PVSV=EV−PV
- Interpretation:
- SV > 0 (Positive): Ahead of schedule
- SV < 0 (Negative): Behind schedule
- Cost Performance Index (CPI)
- Efficiency of cost utilization.
- Formula: CPI=EVACCPI=ACEV
- Interpretation:
- CPI > 1: Cost-efficient
- CPI < 1: Cost overrun
- Schedule Performance Index (SPI)
- Efficiency of time utilization.
- Formula: SPI=EVPVSPI=PVEV
- Interpretation:
- SPI > 1: Ahead of schedule
- SPI < 1: Behind schedule
Forecasting with EVM:
- Estimate at Completion (EAC)
- Predicted total project cost based on current performance.
- Common Formulas:
- EAC=BACCPIEAC=CPIBAC (if current trends continue)
- EAC=AC+(BAC−EV)EAC=AC+(BAC−EV) (if future work follows plan)
- Estimate to Complete (ETC)
- Expected cost to finish remaining work.
- Formula: ETC=EAC−ACETC=EAC−AC
- Variance at Completion (VAC)
- Expected budget overrun or underrun.
- Formula: VAC=BAC−EACVAC=BAC−EAC
- To-Complete Performance Index (TCPI)
- Required performance to meet financial goals.
- Formula:
- TCPI=BAC−EVBAC−ACTCPI=BAC−ACBAC−EV (to stay within BAC)
- TCPI=BAC−EVEAC−ACTCPI=EAC−ACBAC−EV (to meet revised EAC)
Example Calculation:
- Budget at Completion (BAC): $100,000
- Planned % Complete (after 3 months): 30% → PV = $30,000
- Actual % Complete: 25% → EV = $25,000
- Actual Cost (AC): $35,000
- CV = EV - AC = $25K - $35K = -$10K (Over Budget)
- SV = EV - PV = $25K - $30K = -$5K (Behind Schedule)
- CPI = EV/AC = 25/35 ≈ 0.71 (Cost Overrun)
- SPI = EV/PV ≈ 0.83 (Delayed)
- EAC = BAC/CPI = $100K/0.71 ≈ $140,845
- VAC = BAC - EAC ≈ -$40,845 (Expected Overrun)
Benefits of EVM:
✔ Early warning of cost/schedule issues.
✔ Supports data-driven decision-making.
Does this idea interest you? |
The ideas in this development list are jobs either been added by us, or suggested by customers. But we have ranked them with a Marketability Rating so that we can prioritize our development. But you are are interested in getting this development done sooner, you can request for this development (or something similar) by adding a job to the Ticket Request System. For more information on the Odoo App Development process, and the ways we offer to save you money on developing your Odoo System you can have a look at our website at https://interacct.com.au/odoo/apps/ |
Internal Reference:
Was this article helpful?
That’s Great!
Thank you for your feedback
Sorry! We couldn't be helpful
Thank you for your feedback
Feedback sent
We appreciate your effort and will try to fix the article