Cost Taken Up on Invoices for WIP Balance Control

Created by Paul Rainbow, Modified on Tue, 4 Mar at 9:10 PM by Paul Rainbow


Getting a figure of Work in Progress (Costs remaining to be invoiced) is important to find out for most customers, it is one of the important factors.

For customers who only have one invoice on completion of the job this is not important. As WIP can be calculated by looking at the Costs on the Work in Progress Jobs.

But for jobs which have multiple claims, we should take up the "Costs to Date" on each invoice which is generated writing off the Costs at that time.

So we will need a field on the Invoice Form for "Costs Taken up$" which will default to the current WIP Balance on the Job (Actual Costs - Prior Costs Taken Up)

This field should be on input and allow you to adjust the amount you want to take up.

Then when running a WIP Report, we can remove the "Cost Taken Up" on Invoices from the Total WIP Balance.



Does this idea interest you?

The ideas in this development list are jobs either been added by us, or suggested by customers. But we have ranked them with a Marketability Rating so that we can prioritize our development.


But you are are interested in getting this development done sooner, you can request for this development (or something similar) by adding a job to the Ticket Request System.


For more information on the Odoo App Development process, and the ways we offer to save you money on developing your Odoo System you can have a look at our website at https://interacct.com.au/odoo/apps/

Internal Reference:

https://odooappsbyinteracct.freshdesk.com/a/tickets/700215

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article